Here is an ongoing
chronicle of domestic and
overseas contracts involving Indian
companies in April 2008. (Key: entity placing
the order, entity receiving the order)
[Click here for
archives]
A. Domestic Contracts
30 Apr 08
- Hindustan
Construction Co received a letter of intent from
Lanco Infratech for execution of (Lot-IV) all civil works of power
house, surge shafts, pressure shafts, switchyard & tail race tunnels including
adits - IV & V near Subin Khore for 4x125 MW Teesta Hydroelectric Project,
Stage VI in Sikkim. The value of the contract is Rs.303.03 crore and the work
order is to be completed in 44 (forty four) months from the date of LoI. (project
details)
29 Apr 08
- Deep
Industries received letter of award from
Oil & Natural Gas Corporation for deployment of following
compressors for compressing the natural gas at various locations of
Rajahmundry Asset. The approximate value of contract aggregates to Rs.4.15
crore and the following compressors will be installed at
- Lingala [contract value: Rs.2.24
crore]
- Odalarevu [contract value: Rs.0.79
crore]
- Gopavaram-EPT [contract value:
Rs.1.1 crore]
28 Apr 08
25 Apr 08
- Era Infra
Engineering secured contract worth Rs.60 crore from
Lanco Infratech for general civil works (I
& III packages) for the 2x600 MW Anpara thermal power project in Sonebhadra
district of Uttar Pradesh. (project
details)
24 Apr 08
23 Apr 08
- PBA
Infrastructure bagged orders from
-
Maharashtra Industrial Development Corporation for providing
asphalting to roads including widening In A, C, D, E, F & X layout at Nagpur (Higna)
Industrial Area. [contract value: Rs.9.50 crore]
- Surat
Municipal Corporation for construction of concrete pavement and
allied works within Surat city limit for Package - III, (Udhna Magdalla &
Adajan Road) [contract value: Rs.35.43 crore] (project
details)
21 Apr 08
- Saag RR
Infra bagged an order worth Rs.288 crore from
Oil & Natural Gas Corporation for charter hire of offshore
modular workover rig 'SAAG Pacific'; and 'SAAG Saffron'. The contracts are for
a firm period of three years from the commencement date, which is 270 days
from the date of the firm order.
20 Apr 08
18 Apr 08
- Petron
Engineering Construction received letter of intent from
Utility Energytech & Engineers for
erection, testing, commissioning and handing over of critical piping package
for 2 x 300 MW Rosa thermal power project in Uttar Pradesh. The order is
valued at Rs.9.44 crore. (project
details)
17 Apr 08
- Vadodara-based
Permionics Membranes bagged a contract
worth Rs.36.75 crore from Rashtriya Ispat Nigam
for turn-key execution of their sewage and waste water treatment plant at its
Vishakhapatnam steel plant. The scope of work includes setting up a plant for
recycling of treated water using ultra-filtration and reverse osmosis membrane
technology, to produce quality recycle water. (project
details)
16 Apr 08
15 Apr 08
- Kirloskar
Brothers received a letter of acceptance from
Damodar Valley Corporation for the water system package at 2x500
MW Koderma thermal power project - Stage I (2x500 MW) in Jharkhand. The total
value of the contract is Rs.166.77 crore. (more
news) (project
details)
09 Apr 08
08 Apr 08
- C&C
Constructions bagged a contract valued at Rs.574 crore from
Jaypee Associates for construction of road
for the Zirakpur-Parwanoo section a length of 28.69 km on NH-22 in Patiala
district of Punjab and Solan district of Himachal Pradesh on BOT basis. (more
news) (project
details)
07 Apr 08
- RITES
bagged an order worth Rs.47 crore for project management and construction of
railway siding at NTPC's Dadri expansion
power project on a nomination basis. The scope of the work involves management
and construction of the railway siding and signaling and telecommunication
(S&T) system for the project. The work is expected to be completed within 20
months from the date of letter of award. RITES will also be required to
undertake design and construction of the CW Channel/Duct crossing, which is
scheduled to be completed within 36 weeks from the date of award. (project
details)
- Petron
Engineering Construction received a letter of intent from
Bharat Oman Refineries for mechanical
works for HCU/DHDT for Bina Refinery in Madhya Pradesh. The contract is valued
at Rs.84.27 crore. (project
details)
04 Apr 08
- Diamond
Cables bagged an EPC turnkey order for Implementation of Rajiv
Gandhi Gramin Vidyutikaran Yojna (RGGVY) for Mehsana and Patan districts of
Gujarat. (more
news)
03 Apr 08
- A consortium of
Sadbhav Engineering in a 52:48 joint
venture with Gokul Krishna Construction
bagged an order worth Rs.166.88 crore from Government of Andhra Pradesh
Irrigation and CAD Department for earth work excavation, forming embankment
and construction of CD & CM works of main canal and distributory system up to
water course level and CC lining to main canal and other allied works
including investigation, designing and estimation of Gouravelly Right side
canal from KM 0.000 to 47.725 and left side canal in Karimnagar district. (project
details)
- NCL
Industries received orders aggregating to Rs.50.25 crore from
Andhra Pradesh Health & Medical Housing &
Infrastructure Development Corporation for construction of pre fab
structures. These structures will house the campuses of the APIIT (Andhra
Pradesh Indian Institute of Information Technology) at three locations in the
state of Andhra Pradesh and will cover an area aggregating to over 6 lakh sq.
ft.
02 Apr 08
- Era Infra
Engineering bagged an order worth Rs.4 crore from
Jeet Builders for supply of ready mix
concrete for the construction of multi storied residential complex at Greater
Noida.
- Kilburn
Engineering received a letter of Intent from
GHCL for manufacture of 600 tpd calciner for light soda ash. The
order is valued at Rs.11 crore.
- Subhash
Projects & Marketing bagged an order worth Rs.329.48 crore from
NTPC for execution of main plant, CW &
offsite civil works package for 3X 250 MW Bongaigaon thermal power project at
Salakati in Assam. (project
details)
01 Apr 08
- Sunil
Hitech Engineers bagged projects amounting to Rs.100 crore which
constitutes structural works for NTPC Tamil Nadu
Energy Co's 1,000 MW (2x500 MW) coal based power project at Ennore.
[contract value: Rs.90.2 crore] and structural works at Bellary worth Rs.10.4
crore through JSW Steel. The work orders
are to be completed within the period of 15 to 36 months.
- Pratibha
Industries secured a contract worth Rs.37 crore from
Sunshine Housing Development for
construction of a commercial building - Sunshine Towers - at Dadar (West) in
Mumbai. The commercial building will have basement + 41 floors in structural
steel work. The work order is to be executed in 18 months.
B. Overseas
Contracts
------------