ABB, bagged a contract worth Rs.295 crore
from JSW Energy (Ratnagiri) for setting up a 4 x 300 MW coal based power plant
at Jaigad in Ratnagiri district. The contract are for a range of power solutions
including, electrical balance of plant, 400 kV gas insulated switchgear (GIS)
substation and generator transformers.
The 400kV GIS substation will provide
substantial space saving due to its compact design. With all live parts enclosed
and protected against negative influences the gas insulated switchgear ensures
enhanced operational reliability and safety. ABB's scope of delivery also
includes 20/420 kV generator transformers.
ABB's solutions for the project
comprise several leading edge power technologies for improved system efficiency.
The modular eBoP solution for 300MW generating units will provide optimised and
integrated solutions for complete plant electricals including shunt reactors,
bus ducts, control and relay panels, MV and LT switchgear, other auxiliary
systems and four 20kV generator circuit breakers (GCB), thus providing a further
boost towards GCB scheme usages by thermal power plants in India.