Nagarjuna Construction Co has secured
four orders aggregating to Rs.443.50 crore. This includes orders from
- Superintending Engineer, Medium
Irrigation Projects Circle, Bellampally, Adilabad district for
Pranahita-Chevella lift irrigation scheme to be completed over a period of 30
months. [contract value: Rs.107.70 crore] (project
details)
- Chief Engineer, PHED, Jodhpur,
Rajasthan for execution of works related to supply of water from Umed Sagar
Clear Water Reserviour to 170 villages and one town, to be completed over a
period of 75 months. [contract value: Rs.219.10 crore]
- Chief Engineer, MSRDC, Aurangabad
for design and construction pf proposed ROB at railway KM 831/14-15 for
crossing on Mumbai-Howrah Main Link of Central Railway near Narendra Nagar, to
be completed over a period of 18 months. [contract value: Rs.31.80 crore]
- National Institute of Technology,
Warangal, Andhra Pradesh, for construction of hostel buildings, to be
completed over a period of 18 months. [contract value: Rs.84.90 crore]