Elecon Engineering Co bagged various
orders totaling to Rs.524.20 crore. This includes two orders worth Rs.400 crore
for supply of plant and equipment for raw material handling system package for
designing, engineering, manufacturing, procurement, inspection, assembly,
painting, shop testing, supply of plant and equipment including additional
equipment, commissioning spares, freights and transit insurance on for site
basis from Bramhani Industries.
Two other orders are from Bharat Heavy
Electricals for Rs.68.69 crore for designing, engineering, supply and
transportation of mechanical equipments and receipt, storage, transportation,
erection, testing, commissioning & PG test for 500 MW
Sikka thermal power project.
The company received an order for
Rs.31.24 crore for supply of equipments for integrated coal handling plant unit
3& 4 for 600 MW
Rosa Thermal power plant from Tecpro Systems.
Elecon also bagged two overseas
orders. The first order is for Rs.21.54 crore for two stackers/ Reclaimers for
DRI Plant to be installed in Sadat City, Arab Republic of Egypt from Sponge Iron
and Steel Co., Egypt.
The other order is from Indonesia fro
PLTU I Jawa Tengah 2X300-400 MW Coal fired power plant at Rembang, JawaTengah,
Indonesia from PT. Tecgates Engineering of Indonesia.