Bharat Heavy Electricals bagged a
Rs.1,155 crore contract from GVK Power for the supply and
installation of the main plant package for 2x270 MW Goindwal Sahib coal based
power project in Tarn Taran district, near Amritsar in Punjab.
BHEL's scope of work in the contract
includes design, engineering, manufacture, supply, erection and commissioning of
steam turbines, generators, boilers, associated auxiliaries and electricals,
besides state-of-the-art controls and instrumentation.
For the contract, the boiler and its
auxiliaries will be manufactured by BHEL at its Tiruchirapalli and Ranipet works
in Tamil Nadu, while the steam turbine and generator will be manufactured at the
company's Haridwar plant. The pumps and heat exchangers will be manufactured at
its Hyderabad plant and electricals at the Bhopal plant, while the controls and
instrumentation system will be supplied by BHEL's Electronics Division,
Bangalore.