BHEL has won a
third contract worth Rs.1,325 crore from
the Andhra Pradesh Power Generation Corporation(APGenco) for setting up a
1x600 MW thermal power generating unit at Kakatiya Thermal Power Project
Stage-II at Bhoopalapally in Warangal district of Andhra Pradesh.
BHEL's scope of work
includes design, engineering, manufacture, supply, erection and commissioning of
steam turbines, generators, boilers, associated auxiliaries and electricals,
besides state-of-the-art Controls & Instrumentation (C&I). The unit is slated
for synchronisation in 42 months.
Boiler and its
auxiliaries will be manufactured by BHEL at its Tiruchirapalli and Ranipet works
in Tamil Nadu, while the steam turbine and generator will be manufactured at the
company's Haridwar plant. The
pumps and heat exchangers will be manufactured at its Hyderabad plant and
electricals at the Bhopal plant, while the state-of-the-art
controls and instrumentation system will be supplied by BHEL's
Electronics Division, Bangalore.
APGenco has
earlier placed a contract
with BHEL for setting up a 500 MW thermal power generating unit at the
Stage-I of the same power station.