L&T has bagged an order from Arshiya International for building the Phase I
of its upcoming Free Trade Warehousing Zone (FTWZ) in Panvel - Sai Village near
Mumbai.
The order covers complete civil works for Pre-Engineered Building warehouses,
with 'A' class specifications and amenities, container yard (CY) & supporting
infrastructure.
Phase I of CY and supporting infrastructure is likely to be operational by
February 2010 and the first three warehouses, measuring approximately 350,000 sq
ft (with 13 mtrs high state-of-the-art G+7 racking systems) in the warehousing
zone to be operational by March 2010.
The master planning, detailed design and engineering of this FTWZ was done by
STUP Consultants.
On the other hand, work of land development, boundary wall and other
infrastructure is ongoing and is to be completed by 30 September 2009. Tata
BlueScope Steel has been awarded the contract for the PEB structures.