Sadbhav Engineering through its SPV Hyderabad Yadgiri Tollway, has achieved
financial closure on 23 March 2010 for the Hyderabad-Yadgiri road project in
Andhra Pradesh.
The estimated cost of project is Rs 480 crore wherein debt component is Rs
380 crore and balance of Rs 100 crore is equity.
The scope of work includes design, engineering, construction, development,
finance, operation and maintenance of four-laning of Hyderabad- Yadgiri Section
from km 18.600 to km 54.000 of NH-202 under NHDP Phase-III on DBFOT basis.