Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

CCI nod for highway projects

Friday, 09 Apr 2010
Share this on :

The CCI on 8 April 2010 gave a go ahead for implementation of five national highway development projects at an estimated cost of about Rs 4,355.1 crore on a DBFOT basis.

The projects include four laning of 50.6 km stretch in Patna-Bakhtiyarpur section in Bihar, which has an estimated cost of Rs 605.82 crore. The concession period is 18 years, including construction period of 910 days.

Two projects from Rajasthan - which are contiguous stretches - that were approved are four laning of Beawar-Pali section and Pali-Pindwara section. The total project cost of Beawar-Pali section is estimated at Rs 1,102.10 crore, with a concession period of 21 years, including construction period of 30 months. The total project cost of Pali-Pindwara section is estimated at Rs 1,326.54 crore. The concession period is 19 years, including construction period of 30 months.

Further, four laning of the Deoli-Kota section in Rajasthan at an estimated cost of Rs 658.64 crore has also received the nod. The concession period is 26 years, including a construction period of 30 months.

The fifth project is in Uttar Pradesh/Haryana border -Yamunanagar-Saha-Barwala-Panchkula - in Haryana. The total project cost is estimated at Rs 662 crore. The concession period is 21 years, including a construction period of 30 months.