The government of Andhra Pradesh has
invited bids under local competitive bidding, for the Kurnool Cuddapah Canal (K
C Canal) Modernisation Project in the state.
Bids have been invited for the following
works:
Ø
Earth work excavation and cement
concrete lining of distributaries including reconstruction / repairs to
structures lying between km 234.560 to km 290.024 of Kurnool-Cuddapah Canal
package. The cost of the work is approximately Rs.17.892 crore and the period of
completion is 26 months.
Ø
K C Canal Modernisation Project – On-farm
development and formation of Ayacut roads including construction of structures in
Reach no.4 and 5 of K C Canal. The cost of the work is approximately Rs.7.215 crore
and the period of completion is 26 months.
The last date for submission of bids is 10 December 2001.
Bids may be submitted to:
The Superintending
Engineer,
GNSS Circle
TGP Colony,
Cuddapah,
Cuddapah
district,
Andhra Pradesh.
Pin – 516 004
Tel: 08562 43361