Karnataka Power Transmission Corpn. is setting up 1x10 MVA, 110/11 kV substation at Thyagarthi in Shivamogga district of Karnataka.
The project also comprises construction of 110 kV SC line on DC towers with Lynx conductor from 110 kV Shivamogga-Sagara (SS2) line to proposed 110 kV substation at Thyagarthi for distance of about 11.662 km at proposed substation.
The work on the project was commenced in March 2022.
As per the information shared with Projects Today, around 15 per cent work on the project has been completed.