Gupta Energy is setting up three plants under non-conventional energy, as
told to ProjectsToday.
The company is setting up a 10 MW biomass based power unit at
Devali in Wardha district of Maharashtra; and two solar power units of 50 MW
each in Jaisalmer district of Rajasthan (first
plant,
second plant).
Work on the Wardha plant is underway with completion scheduled for July 2011.
Meanwhile, the company has received necessary approvals for the Jaisalmer
projects and is awaiting land allotment from the state government.
Besides, the company's
Phase I 120 MW (2x60 MW) coal based power plant at Ghugus is slated for
completion in April 2011. The
Phase II 540 MW (2x270 MW) supercritical technology based power plant at
Ghugus in Chandrapur district of Maharashtra is to go on-stream in December
2011.
prjexcl