Reliance Petroleum has announced that
the company has successfully completed the first year of implementation of its
refinery complex, being built in a special economic zone at Jamnagar. The
refinery project was kicked off in December 2005.
The refinery project has made rapid
strides on all, including physical progress at the site and has achieved several
key milestones during the first year itself. Significant accomplishments since
the project kick-off include the following:
- All statutory approvals, including
SEZ approvals, have been obtained.
- The equity financing of the project
is completed through a highly successful IPO that established several new
records in the Indian capital markets.
- Through successful global
syndication, the company obtained commitments for $2 billion of debt, which
is the largest foreign currency financing for any single project from India.
- The company concluded a strategic
partnership with Chevron.
- Basic engineering and a major part
of detailed engineering is complete.
- All long lead and critical
equipments have been ordered and remaining procurement / contracting
activities are nearing completion.
- Construction work at site has
taken-off and is progressing at a rapid pace.
The project site with civil,
structural and mechanical works is in full swing. The company has developed
sufficient site infrastructure to sustain construction on fast track and is
ready to receive peak implementation workforce required for the project. The
project is scheduled for completion by December 2008.
Nearly two-thirds of detailed
engineering work is complete and a substantial part of concrete, underground and
structural steel drawings have been released to the site. A massive 3D site
modelling effort is underway and is expected to provide benefits of superior
engineering quality, reduced construction interferences and minimum rework at
site. Over 7,500 engineers are working on the project at several interconnected
locations across the globe.
On the procurement front, all long
lead and critical equipments have been ordered and a substantial part of overall
procurement and contracting activities has been completed. Equipment deliveries
have commenced and more than 80 percent of structural steel and a significant
part of piping materials have also been delivered to the site. Emphasis has now
shifted towards vendor monitoring and follow-up or ensuring compliance with
quality and delivery commitments.
The construction activities have
gained further momentum with over 6,00,000 cubic meters of concreting already
completed (equivalent to several scores of skyscrapers). The month of December
2006 witnessed the creation of a flew record with over 1,68,550 cubic metres of
concrete poured in a single month. Through this, the company has even surpassed
the record created during the implementation of the RIL's refinery at Jamnagar.
Structural works have taken off with more than 30,000 tonne of steel and tankage
fabrication work being completed.