Vadodara-based Jyoti has bagged a hydro power order from Sardar Sarovar Narmada Nigam.
The Rs 422.98 crore order has been bagged in a joint venture with Hyderabad-based Megha Engineering & Infrastructures (MEIL).
The order is for complete EPC of civil, electro-mechanical and hydro-mechanical work including five years operation and maintenance for the Saurashtra Branch Canal Project in Mehsana district of Gujarat.
Jyoti’s portion in this order will be about Rs 100 crore for supply of electro-mechanical equipment.
The hydro power project includes three power houses on the Saurashtra branch canal having nine numbers of five MW full Kaplan machines totalling 45 MW capacity.
Jyoti will be responsible for the electro-mechanical work including the turbine-generator with all auxiliaries and PLC-based SCADA system for fully automated operation of all power houses and switch yard. Complete turbine generator sets will be designed and manufactured at Jyoti's Vadodara factory. The project is proposed to be completed within 24 months.
The company has received major orders totalling about Rs 441.06 crore since April 2014 till date.
In addition to the Sardar Sarovar Narmada Nigam order as mentioned above, major orders received since April 2014 include: 51 crore from NCC for Sauni Yojana Link 3, Package 1; Rs 49.04 crore from NCC for Sauni Yojana, Link 3, Package 2; Rs 95 crore from G Shankar for Koppal Lift Irrigation Scheme, Stage2; Rs 4I crore from NCC for Chambal Bhilwara Water Supply Project, Phase-I, Package-I; Rs 15.21 crore from NTPC for Vindhyachal STPP; Rs 9.22 crore from NTPC for Solapur STPP; Rs 11.95 crore from RRVUNL; Rs 16.30 crore from GETCO for VCB Panels etc.