Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

Kudankulam nuclear power plant delay to lead to cost escalation

Wednesday, 07 Dec 2011
Share this on :

Delay in completion of NPCIL’s nuclear power project at Kudankulam in Tirunelveli district of Tamil Nadu, might lead to cost escalation.

The approved completion cost of the nuclear power project was Rs 13,171 crore. However, the completion cost is now expected to be Rs 15,824 crore and the project is expected to be completed in 2012-13. The delay has been caused due to various reasons including delivery schedule of certain components from Russia and the ongoing protests in Kudankulam against the nuclear power plant.

In 2010, NPCIL and Russia's Atomstroy Export formally signed a deal for building two more civil nuclear reactors of 1,000 MWe each at Kudankulam. A total of 12 Russian nuclear power reactors are expected to come up in India of which six will be built between 2012 and 2017.