Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

NIAL in-principal approves land acquisition process for 3&4 phases of Noida airport

Friday, 17 Feb 2023
Share this on :

The Noida International Airport (NIAL), the UP government’s special purpose vehicle for the project, gave its in-principle approval on 16 February 2023 to initiate the land acquisition process in 14 villages. The acquisition of 2,053 hectares for the third and fourth phases of the Noida international airport will begin soon.

Of these 14 villages, Thora will account for the biggest land parcel with 639 hectares. In Neemka Shahjahanpur, 307 hectares will be acquired, followed by Khwajpur (292 hectares) and Ramner (235 hectares).

In November 2022, the state cabinet sanctioned the acquisition of land for the third and fourth phases of the airport project. Around Rs 6,300 crore would be spent on acquiring the land.

The UP government has made land provisions for all four phases until 2070. In the third and fourth stages, 1,318 and 735 hectares will be acquired, respectively. Around 700 hectares will be used to develop an aviation hub, where factories will be built to manufacture aircraft engines and other parts. Currently, the majority of aircraft parts are manufactured abroad.

Zurich AG is building the first phase of the airport, with operations expected to begin in March 2024. The acquisition of 1,365 hectares for the second phase is currently underway. Among these 1,365 hectares, 1,182 hectares are being acquired in six villages. The remaining 183 hectares are government land chunks.

The Noida international airport, which spans 4,752 hectares, is set to become Asia's largest airport in the coming years. Aside from the main terminal, the airport grounds will house a cargo hub, an MRO facility, and an aviation manufacturing hub, with the goal of attracting international manufacturing companies to set up shop here.