Punj Lloyd has bagged an order from Nagarjuna Oil Corporation for
installation of Inside Battery Limit (ISBL) units and interconnection Pipe Rack
at Cuddalore refinery project in Tamil Nadu.
The scope of work involves construction related procurement, building and
civil work, structural work including prefabrication, mechanical equipment
erection including revamp, piping, painting & insulation, NDE services,
electrical & Instrumentation. The order is to be completed in 18 months.