Punj Lloyd in collaboration with Tecnicas Reunidas of Spain has secured an
order worth Rs 2,056 crore from Abu Dhabi Gas Development Company for the Shah
Gas Development Project in Abu Dhabi.
The consortium is expected to execute the gas gathering package for the
project on EPC basis. The package includes development of well pads, flow lines,
inter-pad lines, transfer lines and overhead lines. The project is scheduled to
be completed by August 2014.
On completion, the gas field is likely to pump around 1,000 mmscfd (million
standard cubic feet per day) of feed gas, which after processing will provide
more than 500 mmscfd of fuel gas and 10,000 tpd of sulphur.