Patel Engineering has commenced civil
construction work on the Rs.240 crore 132 MW Teesta
Low Dam Hydroelectric Project (Stage III) in Darjeeling district of West
Bengal. The scope of work involves construction of a 33m high and 140m long
reinforced barrage across the river and 132 MW hydroelectric power station along
with ancillary structures.
The other eight projects being
executed by Patel Engineering are as follows: