Punj Lloyd on 21 August 2006, bagged
an EPC contract worth $290 million (around Rs.1,300 crore) from Libya-based Sirte Oil
Co for two pipeline projects.
The first contract, valued at $149
million involves the construction of the main 34" dia, 98.4 km pipeline
from Tripoli to Melita and a 24" dia, 21 km branch pipeline to the Zawia
power plant The work involves the construction of gas pressure reducing &
metering stations and a compressor station at Melita. The project is scheduled
for completion within 22 months.
The second contract, valued at $141
million, involves completion of the 34" dia, 157 km El Khoms-Tripoii
pipeline, extensive civil, mechanical, electrical and instrumentation work on
the gas pressure reducing, metering & SV stations, compressor stations at
Sidra & Wachkah, telecommunication & SCADA works. The project is
scheduled for completion within 18 months.