Tehri Hydel Power Project: A Profile
(As of 30 January 2001)
he
Tehri Hydel Power Project is being implemented by Tehri Hydro Development
Corporation Ltd. Located in the Tehri Garhwal district of the State, this is the
largest investment project in the State. The project envisages the construction
of a 260 metre high rockfill dam at the intersection of two rivers –
Bhageerathi and Bhalingna. This huge water reservoir, with 1,500 metre wide
base, would irrigate 2.7 lakh hectares of land, and generate 2,400 MW of
hydro-electric power.
The
project is divided into three phases. In the first phase, currently being
implemented at an outlay of Rs.4,657 crore, 1,000 MW of power generating capacity
would be installed through four submerged turbines of 250 MW each. An identical
capacity would be added in the second phase, while the remainder 400 MW
(through surface generators) has been envisaged in the last phase.
The
project implementing agency, Tehri Hydro Development Corporation (THDC), is a
75:25 joint venture between the Union Government and the Uttar Pradesh State
Government, incorporated in July 1988. The project, conceived as the State
government’s responsibility, was transferred to THDC in June 1989. The Union
Government cleared the project in March 1994 and made an annual commitment of
Rs.300 crore towards the project cost.
The
project that experienced a delayed start (See Tehri Dam: Environmental Issues) is
currently under active implementation. As per latest information available, the
foundation of the main dam has been laid, and this would be increased to a
height of 15 metres. All the four diversion tunnels of the main dam have been
constructed, and so has been the coffer dam. With regard to power generation,
Bharat Heavy Electricals Ltd (BHEL) has been awarded the contract for the
supply and commissioning of power generators.
Meanwhile,
THDC is passively implementing the phase III of the project. This phase entails
the construction of a minor dam that would act as a balancing reservoir to
operate the 400 MW (4x100 MW) surface powerhouse. Global tenders, inviting
pre-qualification bids for this phase, were floated in May 1999. The turnkey
contract entails the supply of the generating plant, auxiliary equipment and
services.
Tehri Dam: Environmental Issues: The Tehri Dam
Project has been in the thick of controversy for the past two decades; the
controversy emanating from environmental issues such as the displacement of
local inhabitants (estimated at around 70,000) and permanent destruction of
agricultural land. These issues, though they sowed the seeds of controversy,
now seem trifling. It is the grave ecological consequence of the project that forms
the backbone of the present antagonism.
Leading geologists strongly feel that the
benefits of the dam are short-lived, and that the construction of the dam can
have devastating effects on the State. They aver that owing to the high
siltation rate (rate at which silt would get deposited into the reservoir), the
life of the dam would only be around 30 to 40 years, as against 100 years
projected by the implementing authorities. This challenges the basic objective
of the project.
More
importantly, the dam is being constructed in a low seismic zone – an area
highly prone to earthquakes. In the
event of an earthquake – a distinct possibility during the lifespan of the dam
– the dam could burst, with a potential of submerging cities like Hardwar and
Hrishikesh.
Protesting local inhabitants and
environmentalists obstructed the project construction work during April and May
1995. The government however overruled the protests on the strength of a
project review carried out in July 1995. The Government, later in June 1996,
constituted a Group of Experts to further examine the safety aspect of the
Tehri Dam. The Group, in its report, stated, “the design of the dam was safe
to withstand the Maximum Credible Earthquake”.
Despite the government’s
repeated assurances about the safety of the project and the fact that the Tehri
Dam Project is very much under implementation, a section of geologists and
environmentalists still feels that a careful reappraisal of the project is
necessary.