Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

NHPC signs contract agreement with Jager-Gammon

Tuesday, 24 Jan 2006
Share this on :

On 24 January 2006, National Hydroelectric Power Corporation (NHPC), signed a Rs.628.92 crore contract agreement with Jager-Gammon for the execution of civil works for the 520 MW Parbati Stage-III Project in the Kullu district of Himachal Pradesh.

The project entails a investment of Rs.2304.56 crores, with debt-equity ratio of 70:30. The equity is being given by the centre in the form of budgetary support and the balance amount is arranged by NHPC from the market, financial insititutions and internal resources.

The project envisages construction of a 43 metre high rock fill dam with a spillway and a 7.25 meter diameter head race tunnel of 7.875 km length. The project is scheduled to be completed in five years and will generate 1963.29 million units of power annually in a 90 per cent dependable year with machine availability of 95 per cent