Punj Lloyd along with JV partner
Persys - Malaysian Co bagged an order worth Rs.142 crore from Delhi Metro Rail
Corpn. for Inderlok - Mundka corridor of Delhi Metro Rail project (Phase
II)
This project involves design and
construction of elevated via-duct of 4.784 km length including structural work
of four elevated stations - Nangloi, Nangloi Railway station, Rajdhani Park,
Mundka on Inderlok - Mundka corridor of phase II.
Work on the project is scheduled for
completion within 30 months from the date of commencement.
The
company had earlier completed a 6.3 km long flyover between Kirti Nagar and
Tilak Nagar as a part of CP-Dwarka Corridor in Phase I of DMRC. It involved
construction of a metro corridor - a height of 17 meters from ground, over the
existing Raja Garden flyover.
Related Links:
Project
profile