Bharat Heavy Electricals bagged a EPC
contract worth Rs.413 crore from Indian Oil Corporation for setting up a
2xFrame-6 gas turbine-based co-generation power plant at its Gujarat refinery
complex.
BHEL's scope of work in the project
envisages design, engineering, manufacture, supply, erection and commissioning
of two Frame-6 gas turbine generators and two heat recovery steam generators (HRSG)
of 100 tons per hour capacity, with associated auxiliaries and balance of plant,
in addition to complete civil works. BHEL will commission the first unit within
a period of 23 months and the second in one month, thereafter.
While the gas turbine generators will
be manufactured at BHEL's Hyderabad plant, the HRSGs and the state-of-the-art
control system will be manufactured at the company's Trichy plant and
Electronics Division, Bangalore, respectively.
Related Links:
Project profile