Larsen & Toubro bagged an order worth
Rs.203 crore from Delhi metro Rail Corporation for the construction of the
underground station at Saket (Delhi) and a tunnel as part of its Delhi Metro
Rail Project (Phase II)
The new station and tunnel will come
up between Central Secretariat and Qutub Minar Corridors of Delhi Metro.
To be completed within 30 months,
Saket station involves 1500m of tunneling and the length of the station will be
284m. In addition, the construction involves a 945m link tunnel and a 260m ramp,
both of which to be completed in 24 months. Top down construction method will be
adopted for the underground station at Saket (Delhi) while cut & cover method
will be used for tunneling and NATM (New Austrian Tunneling Method) for 185m of
twin tunnel.