The documentation work for technology,
safety standards and financials for the Hyderabad metro rail project in Andhra
Pradesh has been finalised.
The Hyderabad Metro Rail have found
that the technical bids of all the pre qualified consortia to be in order and
have declared all of them eligible to participate in the financial bids. The
financial bids is expected to be finalised by March 2008 and the developers will
be chosen by April 2008. Construction work is likely to commence by May 2008 and
is scheduled for completion within four years.