Central Electricity Regulatory
Commission (CERC) has issued the tariff regulations for generation and
transmission projects for the period 2009-14 on 20 January 2009. The new
regulations will also be the guiding principles for the State Electricity
Regulatory Commissions. With the announcement of new norms CERC hopes to attract
the desired investment in power infrastructure in the country while ensuring
that the consumers get electricity at reasonable cost. The following are the
important features of the new regulations:
- The base rate for allowing
return on equity has been raised from 14 per cent to 5.5 per cent to attract
more investment.
- To motivate timely completion
of projects in the present period of power shortages, an additional return on
equity of 0.5 per cent will be available to those projects which are
commissioned within the given timelines.
- By modifying the proposal in
the draft regulations new hydro power projects have been appropriately
insulated from hydrological risk during the first ten years of their
operations. The regulations also allow enhanced free power and rehabilitation
cost according to the new Tariff Policy, with the objective of expediting
project implementation. Tariff for hydro power project has been restructured
to incentivise supply of peaking power.
- Return on equity will be now
pre-tax for which the base rate of 15.5 per cent will be grossed up by applicable tax
rate for the company. This would incentivise investment promotion as the
benefit of tax holiday will be now available to the project developer. On the
other hand, consumers would not have to bear the burden of income tax on the
UI earning, incentive earning and efficiency gains of the projects. This has
been a major grievance of the beneficiaries.
- While doing away with the
advance against depreciation in line with Tariff Policy, depreciation rates
have been reworked to take care of repayment of debt obligations of the new
projects. However, once the initial period of 12 years is over, remaining
depreciation would be spread over the balance useful life to keep the tariff
reasonable.
- Regulatory philosophy of CERC
has been to incentivise efficiency gains and to periodically pass the
improvements to beneficiaries. Accordingly, the availability target for
recovery of fixed cost for thermal power plants has been raised from 80 per
cent to 85 per cent. For the new units, operating margin of only 6.5 per cent
will be permitted with respect to the design heat rate.
- CERC has decided to set up
capital cost benchmarks for thermal power projects and transmission projects.
The provisional tariff has been done away with and the companies will get
final tariff upfront.
- The companies operating
thermal power plants will have now two options. Either they can claim a
special allowance on the basis of per MW per year after completion of
normative useful life of the project and will be obligated to deliver the
norms set for availability and operations. Second option is to go for
comprehensive R&M which is to be permitted by Commission on the basis of
detailed cost benefit analysis including the efficiency gains to the
beneficiaries.
- The incentive available to
the generating companies will now be available on the basis of declared
availability instead of plant load factor because the generators can only
declare better availability and actual schedule is not within their control.