Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

Auctioned wind power projects of 800 MW yet to receive nod

Monday, 07 Oct 2019
Share this on :
Around 800 MW out of 1,200 MW wind power projects auctioned by NTPC in 2018 is yet to receive regulatory approvals. Hero Future Energies, Renew Power, Continuum Wind, Sprng Energy, EDF and Mytrah Energy had emerged as the biggest winners of the auction conducted in August 2018, with tariffs ranging between Rs 2.77 and Rs 2.83 per unit.

The state regulator’s approval for adoption of tariff is required within two months after signing the power purchase agreement (PPA) or the power sale agreement (PSA), whichever is first. But with the power regulators delaying their consent, this period has lapsed and NTPC has given the winners the option of withdrawing altogether.

Approval has not been received for 600-800 MW, so developers are trying to decide if they want to go ahead because the time frame for commissioning, which is 18 months, will not be extended, according to NTPC’s terms.

Among the winners, Mytrah Energy has decided not to commission the project because the state power regulator in Uttar Pradesh has caused a delay. The current delays in adoption of tariffs increase the risk perception of project commissioning delays in future NTPC tenders.

A tender for 1.2 GW of ISTS-connected wind projects from NTPC is currently open for bidding. The delays could result in lower participation from power producers in the new tender.