Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

CESC to set up five thermal power plants

Friday, 12 Mar 2010
Share this on :

CESC plans to set up five thermal power plants with a combined capacity of 5,000 MW over the next few years, with investments in the range of Rs 20,000 crore.

At its 600 MW Haldia plant (West Bengal), CESC is facing land acquisition hurdles. Once the land acquisition is complete, it will take about 33 months for the project to be completed.

Dhariwal Infrastructure, a subsidiary of CESC, is undertaking a 600 MW project at Chandrapur. This project is expected to be completed in another 34 months.

The company is mulling to set up one thermal generation unit each in Bihar, Jharkhand and Orissa. By 2013, the company is hopeful of operationalising at least two of these three greenfield projects.

Also See:

CESC buys majority stake in Dhariwal Infrastructure (29-Aug-09)