Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

JSW Steel to commission 580 MW renewable power by March 2025

Monday, 28 Oct 2024
Share this on :

JSW Steel's Board of directors had earlier approved a power purchase agreement (PPA) for procurement of renewable power totaling to 1,637 MW at Vijayanagar, Dolvi, Salem and Anjar. Of this, 375 MW has already been commissioned, and another 580 MW will be commissioned by March 2025.

The Board has further approved procurement of a hybrid renewable energy (RE) generation capacity of 600 MW (200 MW Solar and 400 MW Wind) at Dolvi in Maharshtra, 60 MW at Salem, Tamil Nadu and 210 MW at JSW steel coated products, taking the generation capacity under procurement to 2,507 MW. The additional capacities will be commissioned in FY27.

Among ongoing projects, the hot strip mill of the five MTPA project at Vijayanagar, set up by JSW Vijayanagar Metallics (JVML), was commissioned in March 2024. The raw material handling system, sinter plant and the blast furnace have also been commissioned, while the steel melt shop is in commissioning stage, and ramp up would happen in Q4/FY25.

At BPSL, the Phase-II expansion from 3.5 MTPA to 4.5 MTPA has been completed and major equipment and facilities have been commissioned. At JSW Steel Coated Products, commissioning activities have commenced at the colour coated line of 0.12 MTPA in J&K. The 30 MTPA slurry pipeline in Odisha is also in progress, with commissioning expected in FY27.