Addendum on 15 May 2006
Mumbai Port Trust has extended the
deadline for submission of financial and technical bids for its Rs.1,200 crore
offshore container terminal project, from 10 May to 15 June 2006.
The Mumbai Port Trust has
further extended the deadline for submission of bids to 10 May 2006 for the
Rs.1,200 crore offshore container terminal project. (Addendum On 12 April
2006)
Original News: 17
March 2006
The Mumbai Port Trust's Rs.1,200 crore
offshore container terminal project has been delayed for the seventh time as the
deadline for submission of global tender has been extended from 15 March 2006 to
16 April 2006.
The deadline is been extended at the
request of the shipping ministry to accommodate Hong Kong-based Hutchison Port
Holdings into the tender. HPH, which will partner with Larsen & Toubro for
the project, is yet to get security clearance from the Indian government,
without which the consortium cannot submit its bid.