The National Highways Authority of India (NHAI) has invited bids for the construction of six-lane elevated corridor in the flood affected zone of Kolhapur on Kagal-Satara section.
The work involves the construction of a six-lane elevated corridor spanning from km 612.582 to km 617.540, including a flyover towards Kolhapur City on NH-48.The contract is expected to be completed within three years, followed by a maintenance period of 10 years. The flood affected zone of Kolhapur, descoped from the original Kagal-Satara Package 1, specifically the second-level ramp construction between km 0.000 to km 1.263.
The contract will be executed under EPC mode, with the closing date for bid submisison set for 18 December, 2025.