HCC has bagged two orders worth Rs 299.36 crore from Hindalco Industries for
structural works for Pot Line for Aditya Aluminium smelter project at Lapanga in
Orissa.
The first order worth Rs 100.36 crore involves design, engineering,
procurement and fabrication and fabrication of Pot Superstructures. The order is
to be completed in 19 months from the date of issue.
The second order worth Rs 199 crore involves complete civil and structural
work invlolving site grading, civil and architectural work for Pot Line. The
order is to be completed in 15 months from the date of issue.