30 Sep 08
- Bharat
Heavy Electricals bagged an order worth Rs.990 crore from
Rajasthan Rajya Vidyut Utpadan Nigam for
setting up a 500 MW (2x250 MW) Chhabra thermal based power unit Phase-II (unit
III and IV) in Baran district of Rajasthan. (more...)
(project
details)
29 Sep 08
26 Sep 08
- McNally
Bharat Engineering secured an order worth Rs.115 crore from
Bharat Heavy Electricals, Bangalore for
design, engineering, supply, E&C and structural steel works of coal handling
plant mechanical equipments for Gujarat State Electricity Corporation's 500 MW
Ukai project. The work order is to be completed in 18 months from the date of
letter of intent. (project
details)
25 Sep 08
24 Sep 08
- Indu
Projects secured an order worth Rs.310 crore from
Uttar Pradesh Rajkiya Nirman Nigam for the construction of Manyawar
Shri Kanshi Ramji Para Medical College in Jhansi. (more...)
23 Sep 08
- Nagarjuna
Construction Co secured four new orders aggregating Rs.413 crore. (more...)
- Lanco
Infratech received a LoI from Andhra
Pradesh Health & Medical Housing & Infrastructure Development Corporation
(APHMHIDC) for construction of buildings for Rajiv Gandhi University of
Knowledge Technologies IIIT at Basara in Adilabad district of Andhra Pradesh.
The contract is valued at Rs.308.98 crore. (project
details)
22 Sep 08
- Roto Pumps
bagged an order worth Rs.3.6 crore from Larsen &
Toubro for Rajasthan Northern Area Development Project of Cairn
Energy India
19 Sep 08
- Metso
Corporation bagged an order worth 14 million euros (approx Rs.91.84
crore) from Tamil Nadu Newsprint & Papers
for supplying a new coking plant and brown stock washing equipment for bagasse
based mill. (more...)
18 Sep 08
- KEC
International bagged two orders for Rs.179 crore for rural
electrification projects in two states. (more...)
- Pratibha
Industries bagged an order worth Rs.156 crore from
Delhi Jal Board for the developing a water
supply scheme. (more...)
17 Sep 08
- McNally
Bharat Engineering Co secured an order worth Rs.87.12 crore from
Damodar Valley Corporation for design,
engineering, supply, erection, testing and commissioning of combined ash
slurry disposal system for both coal based Bokaro thermal power station 'A'
(500 MW) and 20 percent for Bokaro thermal power station 'B' (3X210 MW). (project
details) (project
details)
- Smaarftech
Technologies bagged a Rs.284 contract from
Bihar State Electronics Development Corporation (BSEDC) for a
technology project. (more...)
- Era Infra
Engineering bagged two contracts from
Central Public Works Department worth Rs.123 crore.
(more news)
11 Sep 08
- Era Infra
Engineering bagged a contract worth Rs.208.94 crore from
Naya Raipur Development Authority for
construction of head of department building at capitol complex at Naya Raipur
in Chhattisgarh. (project
details)
-
CCAP bagged an order worth
Rs.19.30 crore from Eastern Railway for
balance work for earthwork in filling and cutting, blanketing and construction
of minor bridges in Section I from Ch. 0.41 km to Ch. 24.55 km for the
connection and construction of New B G. Rail Line Between Manderhill and Dumka-Phase-I
to be completed in 15 months time from 29 August 2008.
10 Sep 08
09 Sep 08
- Carrier
Air-conditioning & Refrigeration (Carrier India) has been awarded
one of India's largest and most prestigious air-conditioning orders from
Delhi International Airport (DIAL) for its
upcoming Terminal 3.
(more news)
(project
details)
08 Sep 08
- Pratibha
Industries secured a contract worth Rs.44.7 crore from
Delhi Jal Board for design and
construction of Unified MS Clear Water Transmission Main from Laxmi Nagar to
Rajiv Gandhi Smriti Van. The project is to be executed in 18 months and
operation and maintenance period for the project will be 5 years.
- ICSA India
bagged orders worth Rs.236.14 crore from Maharashtra
State Electricity Distribution Co (Mahavitaran) and
M PPaschim Kshetra Vidyut Vitaran.
(more news)
- Dolphin
Offshore Enterprises India bagged two orders for Rs.304 crore from
Oil & Natural Gas Corporation.
(more news)
- Patels
Airtemp India received an order of worth Rs.16.09 crore for shell
and tube heat exchangers for Essar Oil's refinery project in Gujarat. (project
details)
06 Sep 08
- BEML
received a Rs.31 crore developmental contract from
Indian Rail Board to design and develop the country's first
stainless steel AC EMU coaches. The scope of work includes design,
manufacture, supply, testing and commissioning of two rakes or 18 units SS EMU
coaches over the next two years.
02 Sep 08
- PBA
Infrastructure bagged a contract for Rs.122.05 crore from
Pimpri Chinchwad Municipal Corporation of
Pimpri for improvement of Aundh-Ravet road.
01 Sep 08
- Gammon
Infrastructure Projects received a LoA from
Himachal Pradesh government for the development of the 261 MW
Youngthang Khab hydroelectric power project on the river Spiti in the Kinnaur
district, on BOOT basis.
(more news)
B. Overseas
Contracts
24 Sep 08
- Simplex
Infrastructure received an order worth Rs.630 crore from Dubai for
a 56 storey commercial complex. The work order is scheduled for completion
within 30 months.
23 Sep 08
- Punj Lloyd
bagged an order worth $800 million (Rs.3,636 crore) from
Qatar Petroleum for the engineering, procurement, installation
and commissioning of strategic gas transmission project.
22 Sep 08
- Punj Lloyd
Upstream, a subsidiary of Punj Lloyd has received a LoI from
Waha Oil Co, Libya, for drilling
exploratory wells in the Gialo oilfield of the prolific Sirte Basin. The
proposed contract is valued at $42 million (approx Rs.168 crore)
(more news)
10 Sep 08
- Larsen &
Toubro secured an equipment order for $160 million (approx. Rs.640
crore) to manufacture and supply 10 hydro treating reactors and 12 coke drums
for Petrobras' prestigious 2,00,000 bpd Northeast refinery project in Brazil.
09 Sep 08
- Punj
Lloyd's wholly owned Singapore subsidiary bagged an order worth
Rs.167 crore from FWP, a joint venture
between Foster Wheeler Asia Pacific Pte and Worley Parsons Pte to carry out
select utilities mechanical works on Jurong Island, Singapore.
08 Sep 08
- Aban
Offshore bagged a contract worth $18 million (approx Rs.79.20 crore)
for the deployment of the new build jack-up rig Deep Driller 7 offshore
Thailand, for a firm period of 3 months, extendable up to 6 months.
- Bilpower
awarded an EPC contract worth $30 million (approx Rs.120 crore) for rural
electrification in Brong Ahafo and Ashanti Region of Ghana. The work order is
expected to complete in 18 months. The contract is backed financially by Exim
Bank of India.
04 Sep 08
- Energy
Development Co received sub-contract for supply of equipment for
Greater Imphal project under APDRP scheme, valued at Rs.51 crore. The order is
to be executed in within 6-8 months.
01 Sep 08
- Indo Asian
Fusegear (IAFL) bagged an order worth Rs.23 crore for supplying
power distribution equipment in West Africa. The order consists of electrical
distribution equipment used in the distribution of power.