Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

ISTS-TBCB development gets major push with scheme approvals worth Rs 29,092 cr

Monday, 01 Sep 2025
Share this on :

The bidding pipeline of the inter-state transmission system under tariff-based competitive bidding (ISTS-TBCB) framework has received a significant boost with six mega schemes worth Rs.29,092 crore cleared by the National Committee on Transmission (NCT) in mid-August 2025.

This marks the largest set of clearances in recent history, both by cost and number of projects. The cleared schemes serve varied objectives: two aim to strengthen interregional transfer capacity, two target renewable energy integration in the southern region, one focuses on power evacuation to green hydrogen/green ammonia plants in Andhra Pradesh, while another will evacuate hydropower from upcoming projects in Arunachal Pradesh’s Siang basin.

The projects have been evenly distributed between bid process coordinators PFC Consulting (PFCCL) and REC Power Development & Consultancy (RECPDCL), with bidding to commence post Union Power Ministry’s final approval. Collectively, they involve over 5,000 ckm of transmission lines and 48,000 MVA transformation capacity, covering western, eastern, northeastern, and southern grids.