Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

Odisha Discoms spend Rs 550 cr on capex

Wednesday, 17 Jun 2015
Share this on :

Power Distribution Companies (discoms) have spent Rs 550 crore on capital expenditure programme in Odisha.

 

The programme was aimed at pruning high AT&C (aggregate technical & commercial) losses.

 

The first phase of Capex, which is expected to be completed by this fiscal end, will see expenditure of Rs 970 crore as per the detailed project report (DPR) prepared for the scheme.

 

Discoms

Expenditure (Rs Crore)

Central Electricity Supply Utility of Odisha

246

North Eastern Electricity Supply Co of Odisha

120

Western Electricity Supply Co of Odisha

107

Southern Electricity Supply Co of Odisha

  77

 

The Capex programme also involved laying of 2,684 km of 33 kV new lines, 5,701 km of 11 kV lines and 7,282 km network of aerial bunched cables. Discoms have installed 173 nos. of 33/11 kV substations. Work is in progress for 21 new substations.