The 99 km long road to Mbale currently under construction in Eastern Uganda is already 30 percent complete in seven months. The schedule for completion of project is 25 months.
The road which stretches from Tirinyi through Nakalama and ends in Mbale, a total distance of almost 100 km, is being constructed by Dott Services. The project involves improvement of the subgrade with G30 grade grave while in narrower sections the road will be widened and benching done to ensure a 9.6 mtr road width which will allow for a seven mtr carriageway and shoulders.
The road construction will also involve replacing all the metal culverts which had deteriorated over time or had been vandalized. Dott Services is also involved in the construction of Arua Town Water and Sanitation project, Kampala main sewage and pipeline project and construction of power lines across the country, among other projects.