Ashoka Buildcon has bagged a contract worth Rs 539.35 crore from North Western Railway (NWR).
The order for the upgradation of the electric traction system along key sections in the Ajmer Division,a nd involves the design, supply, erection, testing, and commissioning of a dual 25 kV electric traction system, enhancing the existing infrastructure to support 160 km/h speeds. The project spans a total of 660.81 RKM (route km) / 1200.85 TKM (Track Kilometer) across sections AII-COR, COR-UDZ, MD-BWA, and BWA-PNU.
Ashoka Buildcon is expected to complete the project within 24 months from the issuance of the letter of acceptance (LoA).