Work on Phase I of Nandi
Infrastructure Corridor Enterprises' Bangalore-Mysore Infrastructure Corridor (BMIC)
project in Karnataka is likely to be completed by October 2007, if the state
government transfers the required land for the project.
Till date, NICE has received 3,900
acre of the 7,000 acre proposed for the first phase of the expressway, which
includes a 41 km peripheral road connecting NH-7 Hosur Road (near Electronic
city) to NH-4 Tumkur Road (near Peenya Industrial Area). It is learnt that work
on 7 km of the 9.1 km link road is complete and in the first phase of the 111 km
expressway, work on only 1.2 km of 12 km is ready.
The company now needs land on Magadi
Road, Mysore road interchange, Kanakapura interchange, Bannerghatta interchange,
link road, Hemmigepura and Hosakerehalli to complete the work on peripheral and
link roads.