DBL-RAMKY Consortium has received the letter of acceptance (LoA) for the Rs 2,905 crore Rajasthan Water Grid Project.
The scope of work involves construction of a feeder line from Isarda to Khura Chainpura to Bandh Baretha in Bharatpur, with all associated components and 20 years of operation & maintenance under the hybrid annuity model (ERCP-09-TF-8). The execution timeline for this HAM project is 27 months.
In a separate win, DBL-PSP (JV) has secured the LoA for a Rs 1,115.37 cr infrastructure development at Pudussery Central and Kannambra of Palakkad Node, Kerala. The project is part of the Chennai-Bengaluru Industrial Corridor (CBIC) extension to Kochi via Coimbatore and includes design, construction, testing, commissioning, and O&M on an EPC basis with a 42-month completion period. Both contracts and mark a significant boost to the companies’ order books.