Larsen & Toubro Ltd bagged an
order worth Rs.418 crore from the Abu Dhabi Water & Electricity Authority
for the construction of six major electrical substations in the Al Ain sector of
Abu Dhabi.
The scope of work involves supply and
installation 33/11 kV primary substations to the specifications of the
international consultant Mott MacDonald. The work also includes design and
construction of civil building and over 120 km of 33kV cabling. The project is
scheduled for completion within 18 months.
The substations will come up at Al
Muthredh, Al Mezyad South. Al Dhaher South, New Al Qua'a, Al Qattara and Civic
Centre to reinforce the regions power distribution network and help meet the
increased demands for power in the region. Each substation consists of 33 kV gas
insulated switchgear, 11 kV air insulated switchgear, 15 MVA 33/11 IV
transformers, substation control and monitoring system, protection and
telecommunication system, DC System and auxiliaries. The contract also
encompasses design and installation of utilities such as air conditioning and
lightening systems.