Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

KEC International bags Rs.235 cr transmission contract

Monday, 03 Nov 2008
Share this on :

KEC International bagged three orders for Rs.235 crore. This includes

  • The first order is valued at Rs.135 crore from Ministry of Energy and Water Afghanistan for turnkey 220 kV D/C Tajikistan- Afghanistan interconnection project. The lines are to be constructed from Shekanbandar to Kunduz (61.25 km) and from Kunduz to Pul-e-Khumri (95.34 km). The total length of lines is 157 km and the project is scheduled to be completed in 18 months.
  • The second order worth Rs.90 crore is from Power Grid Corporation of India for supply and construction of lines associated  with Chamera (HEP) III transmission system. The two lines to be constructed are 220 kV D/C Chamera III - Chamera Pooling Station Transmission Line (53 km). The lines are to be constructed in  Himachal Pradesh and Punjab. The total length of the lines is 68 km and the project is scheduled to be completed within 18 months. (project details)
  • The CSEB order is a turnkey order worth Rs.10 crore for complete supply of towers, conductor, line materials and installation of 132 kV transmission line from 132/33 kV S/S Kawardha to proposed 132 kV S/S Pandariya. The total length of the line is 37 kms. The line is to be constructed in Chhattisgarh and is scheduled for completion within seven months.