Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

KEC International bags four orders

Thursday, 23 Jul 2009
Share this on :

KEC International has secured four orders worth a total Rs 471 crore, two each from North East Transmission Company (NETC) and West Bengal State Electric Transmission Company Ltd (WBSETCL).

The first two orders from NETC are for the supply of towers, hardware, line materials and construction:

1. Package A3: 400 kV D/C Byrnihat Transmission line-route length 119 km-to be constructed in Meghalaya.

2. Package A4: 400 kV D/C Byrnihat-Bongaigaon Transmission line-route length 203 km-to be constructed in Assam.

The transmission lines are associated with 726.60 MW gas based power plants at Pallantana in Tripura. Both the orders are scheduled to be completed by February 2010.

The two orders from WBSETCL are for the supply of towers, line materials and construction of:

1. 400 S/C kV transmission lines associated with Kolaghat thermal power station on turnkey basis with a total route length of 90.5 km. The duration of the project is 24 months.

2. 220 kV D/C transmission lines from Kharagpur 400 kV substation to Midnapore 220/132 kV substation and 220 kV D/C transmission lines from 400 kV Subhasgram substation to Saltala on turnkey basis. The total route length is 58.5 km. The duration of the project is 18 months.

Also See:

KEC International bags three orders (23-Jun-09)